    4:00 Compton group cont. to work on beam. The hall is presently in controled
    access.

    4:30 The hall is closed but there are problems with the acc.

    6:00 The Compton group finishes their measurements and Arun states
    work on making beam quality checks and will preform an Arc
    energy measurement. This should take a few hours.

    7:45 The optics have been opitmized and the OTR is ok. Now
    getting ready for an Arc energy measurement.

    8:00 Make new ESPACE header files for this new beam energy.

    8:45 Arc Energy measurement finished

    9:20 Beam Ready for EP measurement

    10:30 EP measurement finished

    10:50 Finished Taking Carbon Data