4:00 Compton group cont. to work on beam. The hall is presently in controled
access.
4:30 The hall is closed but there are problems with the acc.
6:00 The Compton group finishes their measurements and Arun states
work on making beam quality checks and will preform an Arc
energy measurement. This should take a few hours.
7:45 The optics have been opitmized and the OTR is ok. Now
getting ready for an Arc energy measurement.
8:00 Make new ESPACE header files for this new beam energy.
8:45 Arc Energy measurement finished
9:20 Beam Ready for EP measurement
10:30 EP measurement finished
10:50 Finished Taking Carbon Data
11:35 Start Taking Elastic Data