    User name Eric Voutier

    Log entry time 00:19:45 on February 8,2000

    Entry number 33078

    keyword=Shift summary


    New Crew on shift: Eric Voutier, Ole Hansen, Dimitri Margaziotis
    ***************

    16:00 Beam is still off

    17:30 MCC calls to inform that the PSS problem is progressing but not still
    resolve. Their estimate is that the beam will not come back before midnight.

    18:30 Program Deputy comes to tell that experts think to have find the PSS
    the problem and are going to reset the whole interlock system... Beam may be
    around 23:00...

    22:00 Beam is back, we start checking the beam parameters and improve them
    when necessary

    HARP scan / Beam spot size: beam was coming back with the same parameters as
    previous runs and with an aspect ratio of 1 to 2. The present ration is

    Results from the scan 395

    **********************************************

    scanner # 5 TJ name=IHA1H03A
    Wire combination H position V position
    # 1 # 2 -330.um 76.um
    # 1 # 3 -246.um 160.um
    # 2 # 3 -246.um -7.um
    weighted average -246.um 76.um
    roll angle -6.315mr -0.362deg 0.000deg
    Absolute beam h position: -246.um (+ means at beam left)
    Absolute beam v position: 76.um (+ means too high)
    Horizontal sigma (um): 109.
    Elliptic approximation:
    (tilt angle is from horizontal axis to major axis)
    Vertical sigma (um): 185.241
    Ellipse tilt angle (deg. clockw.): 93.8639
    Ellipse major axis length (um) : 185.517
    Ellipse minor axis length (um) : 108.937

    **********************************************

    scanner # 6 TJ name=IHA1H03B
    Wire combination H position V position
    # 1 # 2 472.um 44.um
    # 1 # 3 448.um 20.um
    # 2 # 3 448.um 69.um
    weighted average 448.um 44.um
    roll angle 1.877mr 0.108deg -0.350deg
    Absolute beam h position: 448.um (+ means at beam left)
    Absolute beam v position: 44.um (+ means too high)
    Horizontal sigma (um): 106.
    Elliptic approximation:
    (tilt angle is from horizontal axis to major axis)
    Vertical sigma (um): 99.4770
    Ellipse tilt angle (deg. clockw.): 30.2349
    Ellipse major axis length (um) : 108.769
    Ellipse minor axis length (um) : 96.1163

    **********************************************

    23:00 OTR and Raster ---> see separate entries

    23:30 Ready for data taking, increasing the current but the ion chambers trip when
    going beyond 45um. The MCC understanding of that problem is that the OTR is
    responsible for that !!! ?????

    The philosophy is to take 100k data with 40um at the beginning and the end of each
    1M events run with OTR in. For the 1M event runs, remove the OTR and increase
    the current to the highest possible value.

    23:52 Start data taking for kinematics 25

    --- Run record for Kin #25

    Last record from previous runs is :
    Events Sum=3.8M 2bbu sum=320

    This last number looks too optimistic, when applying more strict cuts (especially
    y_tgt cuts) it comes about 50 (2bbu events/M raw events) leading to about 190
    events. The target number of events is then 15M that should lead us to 11 hours
    more of data taking on that point.

    Run#/Start time/End time/Events number/Events Sum/2bbu sum/Comments

    1988 / 23:52 / 00:05 / 100 k / 3.9 M / 192 / OTR in