0800 | 0900 | 1000 | 1100 | 1200 | 1300 | 1400 | 1500 | Total Time | |
---|---|---|---|---|---|---|---|---|---|
Acceptable Beam in Use | 20 | 1 | 1 | 1 | 1 | 1 | 20 | 20 | 6 |
Beam Available but Not in Use | 40 | 0 | 0 | 0 | 0 | 0 | 20 | 15 | 1.25 |
Beam Not Available or Unacceptable | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 25 | 0.416666666666667 |
Accelerator Con- figuration Chage | 0 | 0 | 0 | 0 | 0 | 0 | 20 | 0 | 0.333333333333333 |
Experiment Ready | 20 | 1 | 1 | 1 | 1 | 1 | 40 | 45 | 6.75 |
Planned Config- uration Change | 40 | 0 | 0 | 0 | 0 | 0 | 20 | 15 | 1.25 |
Unplanned Experiment Down | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Hall not ready reasons | |||||||||
Target | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
HRSe | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
HRSh | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Data Acq | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Other | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Comments: Data taking at kin1 with high pressure he3 (160 psi) and arc/ep-energy measurements.e-P is still going on at the end of this shift.
Data Entry by: J. P. Chen