0800 | 0900 | 1000 | 1100 | 1200 | 1300 | 1400 | 1500 | Total Time | |
---|---|---|---|---|---|---|---|---|---|
Acceptable Beam in Use | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Beam Available but Not in Use | 0 | 0 | 0 | 0 | 1 | 1 | 0.5 | 0 | 2.5 |
Beam Not Available or Unacceptable | 1 | 1 | 1 | 1 | 0 | 0 | 0.5 | 1 | 5.5 |
Accelerator Con- figuration Chage | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Experiment Ready | 1 | 1 | 1 | 1 | 0 | 0 | 0.5 | 1 | 5.5 |
Planned Config- uration Change | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Unplanned Experiment Down | 0 | 0 | 0 | 0 | 1 | 1 | 0.5 | 0 | 2.5 |
Hall not ready reasons | |||||||||
Target | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
HRSe | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
HRSh | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Data Acq | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Other | 0 | 0 | 0 | 0 | 1 | 1 | 0.5 | 0 | 2.5 |
Comments: 08:00-12:00 Machine Developement time 12:00-14:30 Problems with Hall-A beam dump 14:30-16:00 Beam tuning and checks
Data Entry by: S. Strauch