Main INDEX
Monthly INDEX
PREV
NEXT
User name Higinbotham
Log entry time 00:20:04 on February26,2000
Entry number 34512
keyword=Shift Summary
4:00 Crew finishing putting target back together.
6:00 Target Cooling has started.
9:00 Q3 Trips as the target cool down is finishing.
The He leave went down to 48%. It is now
returning to its nominal value.
9:15 Target is ready....
10:30 Hall is "swept" and we are going to beam permit.
11:40 MCC reports a problem with the Moller Target.
We have contacted Eugene and he is trying to
fix the problem.
12:00 Problem with Moller target fixed.
12:20 MCC continues to try to make beam