• Main INDEX
  • Monthly INDEX
  • PREV
  • NEXT

    User name adaq

    Log entry time 23:56:00 on March 7, 2000

    Entry number 35864

    keyword=Beam Time Accounting
    Hall A

    3/7/2000 1600-2400
    Experiment #: E89-044
    Shift Leader: Perdrisat C.F.
    Shift Workers: V. Punjabi, O. Gayou

    16001700180019002000210022002300Total Time
    Acceptable Beam
    in Use
    0 30 1 1 1 1 1 1 6.5
    Beam Available
    but Not in Use
    0 0 0 0 0 0 0 0 0
    Beam Not Available
    or Unacceptable
    1 30 0 0 0 0 0 0 1.5
    Accelerator Con-
    figuration Chage
    0 0 0 0 0 0 0 0 0
    Experiment
    Ready
    1 50 1 1 1 1 1 1 7.83333333333333
    Planned Config-
    uration Change
    0 10 0 0 0 0 0 0 0.166666666666667
    Unplanned
    Experiment Down
    0 0 0 0 0 0 0 00
    Hall not
    ready reasons
    Target 0 0 0 0 0 0 0 0 0
    HRSe 0 0 0 0 0 0 0 0 0
    HRSh 0 0 0 0 0 0 0 0 0
    Data Acq 0 0 0 0 0 0 0 0 0
    Other 0 0 0 0 0 0 0 0 0

    Comments: see alog

    Data Entry by: Perdrisat