    Log entry time 08:03:49 on March29,2000

    Entry number 37149

    keyword=Owl Shift Summary

    00:00 Beacause of water leak in injector, the beam will not come to Hall A until the cleanup is finished.

    The spectrometer has been set up to kinematics 23, 1 M events have been
    taken, need to take 15M more events.

    Move the target to empty position for safety.
    Waiting for the beam.

    03:30 EQ3 Quenched. Need access to hall A to reset the EQ3.

    04:25 MCC said they are going to send the pulsed beam to hall in one hour.

    06:00 MCC starts sending CW beam to hall A for test.

    07:00 MCC is still testing the beam.

    07:40 Ask for an access to Hall A to reset the EQ3.

    08:00 finish resetting EQ3.