0000 | 0100 | 0200 | 0300 | 0400 | 0500 | 0600 | 0700 | Total Time | |
---|---|---|---|---|---|---|---|---|---|
Acceptable Beam in Use | 0 | 0 | 0 | 0.17 | 0.5 | 0.5 | 1 | 1 | 3.17 |
Beam Available but Not in Use | 0 | 0 | 0 | 0.5 | 0.5 | 0.5 | 0 | 0 | 1.5 |
Beam Not Available or Unacceptable | 0 | 0 | 0 | 0.33 | 0 | 0 | 0 | 0 | 0.33 |
Accelerator Con- figuration Chage | 1 | 1 | 1 | 0 | 0 | 0 | 0 | 0 | 3 |
Experiment Ready | 1 | 1 | 1 | 0.67 | 0.5 | 0.5 | 1 | 1 | 6.67 |
Planned Config- uration Change | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Unplanned Experiment Down | 0 | 0 | 0 | 0.33 | 0.5 | 0.5 | 0 | 0 | 1.33 |
Hall not ready reasons | |||||||||
Target | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
HRSe | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
HRSh | 0 | 0 | 0 | 0.33 | 0.5 | 0.5 | 0 | 0 | 1.33 |
Data Acq | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Other | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Comments: Took time to reset hadron Q1 and Q3. Planned optics measurements required beam position fast feedback on, which was not available. So the measurements made today should be repeated when FF is available.
Data Entry by: M. Rvachev