• Main INDEX
  • Monthly INDEX
  • PREV
  • NEXT

    User name adaq

    Log entry time 00:20:08 on October 1, 2000

    Entry number 48802

    keyword=Beam Time Accounting
    Hall A

    9/30/2000 1600-2400
    Experiment #: e97111
    Shift Leader: J Templon
    Shift Workers: K Aniol, B Sawatzky

    16001700180019002000210022002300Total Time
    Acceptable Beam
    in Use
    1 1 1 1 1 1 1 1 8
    Beam Available
    but Not in Use
    0 0 0 0 0 0 0 0 0
    Beam Not Available
    or Unacceptable
    0 0 0 0 0 0 0 0 0
    Accelerator Con-
    figuration Chage
    0 0 0 0 0 0 0 0 0
    Experiment
    Ready
    1 1 1 1 1 1 1 1 8
    Planned Config-
    uration Change
    0 0 0 0 0 0 0 0 0
    Unplanned
    Experiment Down
    0 0 0 0 0 0 0 00
    Hall not
    ready reasons
    Target 0 0 0 0 0 0 0 0 0
    HRSe 0 0 0 0 0 0 0 0 0
    HRSh 0 0 0 0 0 0 0 0 0
    Data Ac 0 0 0 0 0 0 0 0 0
    Other 0 0 0 0 0 0 0 0 0

    Comments: optics commissioning very productive shift

    Data Entry by: Templon