    User name rohe

    Log entry time 16:08:28 on Oktober26,2000

    Entry number 50932

    keyword=day shift summary

    8:00 left spectrometer does not move --> controlled access
    cycled left spec. to 3.924
    (beam accounting died)
    8:25 Ed Folt can't move it --> Joe Mitchell decided to go on with CQO-3
    set left spec. to 3.465 back -- moved Left ARM BY ~ 15 VERNIER MARKS
    8:43 RUN 2057 (CQO-3) New angle is 20.758 deg
    9:48 stopped 2057 because beam off (RF communication problem)
    --> controlled access (it took 1 h to get there !) for target change and repair of
    spectrometer rotation
    ~12.30 spectrometer rotation is working now
    The vernier maker for left spectrometer is very hard to read (jitter).
    So I was down and verified that it is actually +32 (for the next H2 measurement (laying on my knees ...)
    16:00 left gas master is bieping: Hadron shield hut has 30 % to blow up (C.3=29%)!
    Target not ready yet but the accelerator is (in principle)